Space X Data Center Power

A. Scope of project

This proposed SpaceX hyperscale data center would be the largest data center ever proposed in Arizona, drawing 6,000 megawatts at full build-out, of which the first phase alone would draw 1,500 megawatts. That is more than eight times the roughly 709 megawatts of installed thermal capacity at the nearby Apache Generating Station (about 625 megawatts in its original units, plus two 42-megawatt gas turbines that AEPCO had procured and constructed by June 2025 and that federal energy-data filings now show as operational, excluding solar and battery resources), and about 7.6 times AEPCO’s actual 2025 systemwide peak demand of 789 megawatts. These are comparisons of scale, not a claim that the Apache station or AEPCO could otherwise supply a project this size. By APS’s estimate of about 160 homes per megawatt, that is enough electricity for nearly a million Arizona homes, in a county of about 126,000 people.

B. Where does the power come from?

AEPCO, which supplies part of SSVEC’s power, says it would serve the campus “through its generation portfolio and, principally, through transmission rights and market access… across the Western Interconnection,” buying “energy from existing generation in neighboring markets that would otherwise sit idle or be curtailed,” while the generation actually needed is still “being studied” (Application, pp. 48–49). Power idle on a spring afternoon may not be available on a summer evening, and buying it on the market would put the project in competition with the region’s utilities during the same summer peaks described in Section E. AEPCO supplies power to five Class A member distribution cooperatives, not SSVEC alone, across Pima, Pinal, Santa Cruz, Mohave, Greenlee and Graham Counties. A draw this large on AEPCO’s shared resources is not contained to Cochise County. AEPCO and SpaceX describe a revenue-sharing arrangement that may also benefit these same cooperatives, but that arrangement, capped at an “up to” figure and subject to final negotiation, does not address whether a buyer of this size competing on the same wholesale market would raise prices or reduce supply for them during shortages. That arrangement is also limited to AEPCO and its own member cooperatives; it does not extend to APS, SRP, or other Arizona utilities that may compete for power in the same regional market and would share in none of its proceeds.

The two other candidate sources are not yet available either. The Southline transmission line is not expected to begin construction until 2027, with its first phase operational by 2028. It would have transmission capacity of about 748 megawatts, a fraction of the project’s 6,000, and it is a transmission line, not a source of generation. If additional generation is gas-fired, the proposed new pipeline most relevant to the project, Energy Transfer’s Desert Southwest Expansion and its proposed 24-mile Apache Lateral, has not been approved and is not expected to be in service until 2029. Energy Transfer, the pipeline’s developer, has said it expects the expansion’s remaining capacity to be fully subscribed once its open season concludes, on top of existing interstate gas pipelines serving Arizona that utilities already describe as fully subscribed (Natural Gas Intelligence); the lateral’s own capacity, and who has contracted for it, have not been disclosed. Depending on the cooling technology, gas-fired generation can also require water for cooling, so any generation built to serve this campus could carry water impacts beyond the campus itself.

The applicant says it would fund the needed grid upgrades itself. The application puts the applicant’s investment in transmission and substation improvements at about $3.6 billion across four phases, paid through an electric energy services agreement with SSVEC and AEPCO, with no cost to existing members (application, pp. 2, 49). AEPCO says a fee on the campus’s wholesale energy would become patronage capital or fund transmission upgrades; SSVEC says a premium on its purchases would build cooperative equity, lower member rates and fund the SSVEC Foundation (application, pp. 2–3, 49–50; Docket No. E-01773A-26-0123). These commitments address who pays, not whether the generation, transmission and gas supply described above will be available when each phase needs it; AEPCO’s own letter says only that Phase 1 is feasible, with later phases still being studied (Section D).

C. On-site and temporary generation

At its November 4 community meeting, SpaceX told residents, “There will be no gas turbines on site. There will be no on-site power generation.” The application nevertheless includes natural gas backup generators of about 10 megawatts per building, roughly 90 megawatts in total. Although these are standby generators rather than primary power plants, gas engines can raise many of the same concerns as turbines regarding air quality, noise, heat and fuel storage.

Dedicated generation at other SpaceX projects. At its Terafab project in Grimes County, Texas, the SpaceX executive who presented this project at the November 4 Cochise meeting said in August 2026 the company was “bringing our own power” and building natural-gas plants and battery arrays; Grimes County’s own reinvestment-zone order confirms a “power plant” is part of that project. SpaceX’s Memphis xAI data centers also rely heavily on gas generation. Those are separate projects in other states, and neither SpaceX nor Tombstone Resources has proposed dedicated generation for this campus. They are relevant because SpaceX told Cochise County residents there would be no on-site power generation, while AEPCO’s letter states that later phases “are expected to require additional generation and transmission facilities” (p. 53), and neither the application nor AEPCO says what that generation would be or where it would be built. The County cannot regulate a power plant in another jurisdiction, but it can require the applicant to disclose what generation would serve the campus, where it is located, whether it has its required approvals, and whether it is actually available.

Temporary fuel supply. SpaceX’s project FAQ describes the intended arrangement as no on-site power plant or fuel yard and no bulk fuel storage, with standby generators supplied by pipeline gas. The application, however, allows a temporary compressed or liquefied natural gas supply if pipeline gas is unavailable when a building opens (p. 25), a fuel arrangement the FAQ does not address. There is no pipeline agreement or schedule (p. 50), and no limit on how long the temporary supply could last or how much fuel would be stored (p. 40). The County’s data center ordinance requires the site plan to identify backup generators “and any associated fuel storage,” yet the application does not show where this fuel would be stored. Because buildings would open in phases over several years, this temporary arrangement could last years.

Temporary generators. The County’s data center ordinance addresses backup generators, their testing and their fuel storage, but it does not mention temporary or portable generation, including during construction. The application does not propose such equipment, but experience elsewhere shows why the gap should be closed. At its Southaven, Mississippi site, xAI, which SpaceX acquired in February 2026, ran trailer-mounted gas turbines without an air permit because the state treated them as temporary and mobile. The number grew from 18 to 69, and some were later allowed to run past the original 12-month limit. In October, a federal judge denied xAI’s motion to dismiss a lawsuit challenging that exemption, allowing the case to proceed. Arizona’s portable-source rule requires operations to be temporary and to involve at least one change of location during the permit term. For Class I sources, the owner or operator must notify the state and relevant county air officials at least 10 days before a move; for other sources, notice is required before the move, without a specified minimum advance period. The rule requires notice to those officials, but does not itself require direct public notification of a move (A.A.C. R18-2-324(C), (E), as amended, 32 A.A.R. 92, Jan. 2, 2026; effective Feb. 7, 2026).

D. Lack of information beyond Phase 1

The application does not demonstrate how power would be provided beyond Phase 1, which requires approximately 1,500 megawatts. Section 2.51.240(5)(i)(1) of the Cochise County Development Service Code states that the applicant “shall demonstrate that adequate utility services are available or will be provided to serve the Data Center without adversely impacting existing users.” Under Section 2.06.010(1)(a), “shall” is mandatory. Section 2.48.160(e)(1) likewise requires the applicant to “demonstrate that there are adequate provisions to address the impacts identified.”

The application seeks approval for 6,000 megawatts, but AEPCO’s letter confirms feasibility only for Phase 1, about 1,500 megawatts. The application says service beyond Phase 1 “may require additional generation and transmission facilities” (p. 48), while AEPCO’s own letter says later phases “are expected to require” them (p. 53), a stronger statement than the application makes. Neither utility guarantees service, even for Phase 1. AEPCO conditions service on “final negotiation and approval of the required agreements… and receipt of applicable regulatory approvals,” and SSVEC’s letter states that it “does not constitute a guarantee of a particular level of service, energization date, rate, or other final service term.” SSVEC’s project website confirms no agreement has been finalized and that protections for existing members are still under negotiation.

A utility letter that does not commit to service is not a demonstration that “adequate utility services are available or will be provided,” so the County cannot make the required finding. The County is being asked to approve the full 6,000-megawatt project without knowing what generation, transmission or other infrastructure would serve three-quarters of it, and the possibility that these facilities may be studied and developed later does not satisfy the requirement. Approving a 6,000-megawatt campus and approving a 1,500-megawatt first phase are different decisions, and the evidence supports, at most, the first phase. If the County considers a phased approval, the approval itself would need to be limited so that later phases cannot proceed until their power supply, transmission capacity and associated infrastructure have been demonstrated and reviewed. Without a demonstration of adequate service for the full project, the application does not meet the code’s requirements as proposed.

E. Grid stability: How would the campus be treated during power shortages?

During this summer’s record heat, peak demand at APS and SRP reached about 90% of the planned power capacity they had reported to the state utility regulator. Texas enacted a 2025 law requiring protocols to allow certain new transmission-voltage loads to be curtailed during firm load shed, with exceptions for specified critical loads.

In Arizona, the Corporation Commission approved a process in August 2026, requested by AEPCO, SSVEC and four other rural cooperatives, for reviewing service agreements with large-load customers such as data centers. Applications must state whether the large-load customer’s power can be interrupted or cut back during shortages, but the process does not require it. Arizona Corporation Commission staff review each agreement on three criteria: whether it is in the public interest, whether its rates are reasonable, and whether other customers would end up subsidizing the large customer. Those criteria do not directly address whether a 6,000-megawatt buyer entering the same wholesale market would raise prices or reduce supply for AEPCO’s other members or other utilities buying on that market, none of whom are party to the agreement. Whether the agreement itself would be filed subject to a non-disclosure agreement is not publicly known. For this project, SSVEC says it is still negotiating with the developer.

The application describes how the campus would ride through a loss of utility power: its backup generators would serve “critical services only (network, controls and life safety),” and “multi-hour battery energy storage” would “cover a longer interruption while utility service is restored” (p. 25). The operations narrative does not say whether the campus would accept curtailment during a regional shortage, or whether it would be treated as firm load that stays on while other customers are cut. Until the service agreement answers that, the County cannot know whether homes, farms and businesses in Cochise County and elsewhere on AEPCO’s system could face outages while the campus keeps operating.